What is the benefit of conducting the 11th Month Walk Through?

Study for the ACG Certified Commissioning Technician (CxT) Test with detailed questions, interactive quizzes, and comprehensive explanations. Enhance your preparation and achieve certification success!

Conducting the 11th Month Walk Through is primarily beneficial for identifying chronic problems before the warranty expiration. This walkthrough serves as an opportunity to assess the performance and functionality of systems and ensure they are operating as intended. By identifying any persistent issues or deficiencies before the warranty period ends, the commissioning team can hold the contractor accountable for necessary repairs or corrections. This proactive approach helps avoid potential costs associated with fixing these problems after the warranty has expired, as issues that are documented and reported before this deadline typically remain the contractor's responsibility.

The other choices, though they may involve different aspects of project management or development, do not directly address the specific benefits of the 11th Month Walk Through. For example, developing new project goals and establishing future project timelines pertain to planning and management stages rather than addressing existing problems. Reviewing contractor credentials focuses more on pre-construction evaluation rather than post-construction assessments, which is the primary function of the 11th Month Walk Through.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy